From the first walk-round to the last test certificate

Seven steps, the same on a single chiller or a full conversion. Each one ends with something signed, so you always know what has been agreed and what is still open.

Isolation sketch Example Isolated P3

The process

Who is in the room, and what gets signed

Hotels have more decision-makers than most buildings. Owner, asset manager, general manager, director of engineering. We name who takes part at each step so nobody hears about a shutdown for the first time on the day.

Each step shows what we do, what you decide or approve, the documents you receive, and, where it differs, what changes in a hospital.

  1. Survey

    What we do

    We walk the building with your chief engineer: plant rooms, risers, the roof, the fire alarm panel and a sample of rooms on each floor type. We read the maintenance logs, 12 months of electricity bills and the last Civil Defense inspection records before we form a view.

    In older hotels we expect drawings to be missing. We trace and draw the plant rooms, risers and a typical floor before we price anything, and we test-close the isolation valves we plan to rely on. Where a valve won't hold, the method uses a pipe freeze or line-stop, or the valve is replaced in a planned drain-down agreed with you, never discovered on the day. In buildings from before 2000, suspect materials such as old pipe lagging, ceiling boards and floor adhesives are sampled and tested before anything is opened.

    What you decide or approve
    Which systems are in scope, and in which year each item is done. You sign off the condition report and the agreed scope of works, and the owner or asset manager approves the CapEx plan.
    Who takes part
    Owner or asset manager, hotel chief engineer, our project manager and MEP engineer
    SURVEY · L9 1–5 Fan coil 905 2 Branch valve V-9S holds Smoke detector 905 1 Floor board DB-9 3 Old pipe lagging lab Walked with: chief engineer A DB-9 Clamp meter
    CT-01Survey sheetLevel 9Example
  2. Design check and coordination

    What we do

    On most jobs we build to your consultant's design and produce the shop drawings; where design is in our scope, the contract says so and the design is stamped by a licensed engineering office. Shop drawings and submittals are checked against the relevant parts of the Saudi Building Code before procurement, and the trades are coordinated in the ceiling void, so a sprinkler branch and a duct never meet for the first time on site.

    Approvals come before anything is ordered. Where the works change fire systems or escape routes, the fire and life safety (FLS) drawings are prepared and stamped by a licensed engineering office and approved by Civil Defense before installation starts. On a brand job, the MEP and FLS drawings and key equipment submittals go to the brand's technical services for review, and their comments are closed first.

    The price is fixed against the signed scope; anything outside it goes through a written variation. What can be measured only once ceilings are open is a provisional quantity at a tendered rate and remeasured on site, such as branch valve replacement (CT-03 line PQ-01) or fire-stopping (PQ-02). What cannot yet be defined is a named provisional sum, such as sprinkler alterations (PS-01), spent only on your instruction, with any unspent balance returned to you in the final account.

    What you decide or approve
    The shop drawings and material submittals, and the contract price against the signed scope. Civil Defense approves the FLS drawings and the brand approves its submittals; we do not issue approvals.
    Who takes part
    Your consultant or a licensed engineering office, your director of engineering, our MEP engineer, project manager and QS; Civil Defense and the brand's technical services for approvals
    Supply duct CHWSCHWR Cable tray C-01 Sprinkler branch Ceiling line C-01 closed: branch rerouted clear of the duct
    CT-05Coordination sectionCorridor voidExample
  3. Phasing plan, with the building kept open

    What we do

    The scope becomes a programme built around your occupancy forecast and events calendar. We decide with you which rooms come off sale and when, where the hoarding goes, how contractors move through the building, and when any shutdown can happen. Floors come out either as a full-floor release, when the work reaches the riser branches, ceilings or bathrooms below, or as part-floor zones behind a sealed hoarding, like the level 9 example below, when the work stays inside the rooms; your phasing plan states which applies to each floor.

    Before work starts, each floor also has its method statement and isolation plan, and an inspection and test plan with the hold points where your engineer can stop us.

    What you decide or approve
    Which rooms come off sale and when, one or two floors at a time, the agreed period for noisy works, and any shutdown night. Your general manager and revenue manager sign the phasing plan.
    Who takes part
    General manager, director of engineering, front office and revenue, executive housekeeper, our project manager
    WK15913172124L12L11L10L9L8L7L6L5L4L3L2 SellingWorksTestingHanded back
    CT-06Phasing stripL12–L2 · 24 weeksExample
  4. Works

    What we do

    Crews we prequalify install under our engineers' daily supervision. Every working day starts with permits and a short coordination meeting with the hotel. Every electrical isolation is locked with a multi-lock hasp: our authorised person fits the isolation lock, every worker in the zone adds a personal lock, and the hotel's duty engineer adds the hotel's lock, so nothing can be re-energised without all three. Circuits are proved dead at the point of work with a voltage tester checked on a known live source before and after (live-dead-live).

    On a refurbishment, one room is finished first as the mock-up and signed off before the floors are built to it. Any change to scope or cost is agreed in writing before the work is done, valued at the rate in the bill, at a rate built from those rates, or by a quotation agreed before the work starts. The baseline programme is updated in each weekly report, and each month the owner or asset manager also receives a cost report: contract sum, approved and pending variations with their SAR value, provisional sums against allowance, contingency drawn and remaining, forecast final cost and a three-month cash-flow forecast, in PDF and Excel.

    What you decide or approve
    Each variation, in writing and before the work is done; the mock-up room; and, at any time, a stop on request: your duty manager can stop noisy work on any floor with one call.
    Who takes part
    Our project manager, QS and HSE/QA lead, specialist subcontractors, the hotel's engineering team, the owner or asset manager for cost
    CHWSCHWR V-9S CLOSED V-9R CLOSED Zone 907–912 Riser live DB-9 123 1 Our authorised person 2 Each worker in the zone 3 Hotel duty engineer
    CT-07Isolation and lock-outLevel 9Example
  5. Testing and commissioning

    What we do

    Pressure tests on pipework, insulation resistance on cables, fire alarm cause-and-effect, air and water balancing on HVAC. Your engineer watches the tests. Where Civil Defense needs to witness, we book it and prepare for it.

    Results are recorded on signed test sheets against the inspection and test plan agreed before work started, zone by zone, so each floor can go back as soon as its own records are complete.

    What you decide or approve
    Your engineer witnesses each test and countersigns the sheet, and the snag list is agreed with you before handover.
    Who takes part
    Our MEP engineer and HSE/QA lead, the hotel's director of engineering, Civil Defense where required
    TEST SHEET · CT-11 SystemCHW · L9 TestHydrostatic Held forPer ITP, CT-08 Result PASS FAIL CORETECH Hotel Civil Def. Witnessed by bar Calibrated test gauge
    CT-11Test sheetCHW branch L9Example
  6. Handover

    What we do

    Two separate sign-offs. Contractually, each zone is handed over to your owner's representative, who issues a taking-over certificate on our project manager's application, so our own work is always signed off by someone else. Operationally, a room goes back on sale only after the snags are closed, a builders' clean and a housekeeping deep clean are done, and the room has passed its return-to-sale checks:

    • Every outlet on the floor is flushed, and hot water reaches 50 °C within a minute at each tap.
    • Water samples are clear wherever the hotel's water management plan requires sampling.
    • The fan coil runs for 24 hours with a new filter, to purge dust and odour.
    • The smoke detector, door lock, safe, TV and phone are tested against the property management system (PMS), and each check is logged on the room's return-to-sale sheet.

    Your chief engineer and executive housekeeper then inspect the room together, and front office changes it from out of order to vacant inspected. While a floor is closed, its outlets are flushed weekly and logged, and new or disturbed pipework is disinfected before use, with the disinfection certificate filed in CT-11.

    Your engineering team gets the drawings, manuals, spares and a walk-through of every new piece of equipment.

    What you decide or approve
    Your owner's representative issues the taking-over certificate for each zone; your chief engineer and executive housekeeper sign each room back to sale.
    Who takes part
    Owner's representative, director of engineering, executive housekeeper, front office manager, our project manager
    O&M 1 O&M 2 O&M 3 CT-16 CT-17 Spares AS-BUILT · CT-15 CT-14 Taking-over certificate ZONE L10 Owner's rep. Two sign-offs: taking-over, then return to sale
    CT-14Handover setZone L10Example
  7. Aftercare and maintenance

    What we do

    Each zone's defects period starts from its own taking-over certificate, so floors finished early aren't left waiting. During that period we come back to put right any defect in our work. Manufacturer warranties are separate from the defects period: they often start at delivery or start-up, so the warranty register (CT-18) records both start dates for each item and shows any gap, which we ask suppliers to close by aligning their start dates. The defects period, retention and payment terms are set out in each proposal.

    After that, if you want us to, a monthly maintenance agreement keeps the same engineers on the systems they installed.

    What you decide or approve
    Your owner's representative accepts the defects close-out. Whether to continue with a maintenance agreement is your choice, with its targets agreed per site.
    Who takes part
    Director of engineering, owner's representative, our maintenance engineers
    Start-up Taking-over CT-18 · CHILLER 1 GAP Manufacturer warranty Defects period PPM year plan, month by month · CT-20
    CT-18Warranty registerOne lineExample

See the seven steps applied to the 176-room reference hotel used on this site, written up in the format we will use for completed projects.

Worked example (illustrative, not a completed project)

Working in a live hotel

One floor, six rooms under works, ten still selling

Our method requires this drawing before work starts on any occupied floor. The example shows level 9 of our reference Riyadh hotel of ground plus 12 floors: 11 guest floors, 16 rooms a floor, 176 rooms. Switch the layers on and off to see how guests and contractors share the floor without meeting.

1 2 3 4 5 6 A B C D 901902903904905 906907908909910 911912913914915916 Elec. Linen Guest lifts Service lift Stair A Stair B Guest corridor Work zone 907–912 · hoarding H-01 QQ D1 D2 D3 D3 N1 P1 P2 P3 P4 4 2004 2004 2004 2004 200 4 2004 2004 2004 2004 200 42 000 8 4001 8008 400 N Example floor · level 9 · rooms 901–916 · scale 1:200 (A3)

Swipe sideways to see the whole floor.

Live-hotel works plan Example L09 1:200 (A3)

Rooms 907–912 come off sale together. A dust-tight hoarding, H-01, closes the corridor just past the lift core. It never blocks an escape route: its door opens outward with a push bar, and the corridor behind it stays clear and lit to Stair B. H-01 is built from non-combustible boards, sealed at the slab and ceiling. Where it closes a corridor that forms part of a fire or smoke separation, it is built to the fire-resistance rating shown on the approved fire and life safety (FLS) drawing, so the corridor's compartmentation stays intact. No guest route passes through the works zone, and any dead end it creates stays within the SBC 201 limit. Temporary exit signs are added where it changes the route, and every penetration we open is fire-stopped and inspected before it is closed.

People, materials and waste use the service lift in the 06:30 slot and a second slot set with housekeeping, then cross two metres of protected corridor straight into the hoarding door. Nobody in work boots walks the guest corridor.

From the guest lifts to rooms 901–906 and 913–916 nothing changes. Guests see a finished, painted hoarding past the lifts, and that is all they see.

Drilling, cutting and chasing happen only inside an agreed period, Sunday to Thursday, with no noisy works on Friday or Saturday. The period is tied to the hotel's own check-out and arrivals and set with your executive housekeeper: it opens after the floor's last check-out and closes before the first arrivals. Late check-outs and day-sleepers, such as airline crew, are flagged in the morning meeting and the start is held back for them. Rooms next to the hoarding (Q), and the rooms directly above and below the work zone, are sold last or held back while noisy works run. During Ramadan the period is reset with the hotel, and there are no shutdowns unless the general manager agrees one in the quiet hours after suhoor. Planned exceptions, such as a crane lift for a chiller swap, are listed in the phasing plan (CT-06) and agreed in writing with the general manager two weeks ahead: a single lift, early on a low-occupancy morning, with the top guest floor held back that night.

Check-out → arrivalsSet with housekeeping, Sun–Thu

D1 negative-air unit, so any leak draws air into the zone. D2 tack mats at the hoarding door. D3 return-air grilles in the fan coil unit (FCU) bulkheads sealed inside the zone. D4 smell: low-odour, low-VOC paints, adhesives and sealants are submitted to you before use; odour-heavy work runs with the negative-air unit on and finishes early enough to purge the zone before guests return in the evening, and the zone's fresh-air and corridor supply is isolated or filtered so nothing travels to selling rooms through the ductwork. N1 noise checked from the neighbouring room during the agreed period. N2 vibration: core drilling and chasing travel through the slab, so we use wet diamond coring and wall saws instead of breakers, test-drill on day one while your duty manager listens from the rooms two floors up and down, and widen the sold-last zone if they can hear it.

P1 Room circuits for 907–912 isolated at the floor distribution board, locked and tagged. The board stays live for the rooms still selling. P2 Fire detectors isolated one by one, at device level, inside the hoarding only, and logged as a fire-system impairment; corridor detection stays live. A fire watch is posted, the hotel's duty manager is informed, and detectors are reinstated at the end of every shift. P3 Domestic and chilled water isolated for the zone without touching the riser, so floors above and below keep pressure: at the branch valves where pipes run along the corridor, or at each fan coil's own valves where the coils are fed from vertical risers. A riser serving a stack of rooms is drained only in a planned shutdown. P4 Sprinklers can't be isolated room by room: the floor control valve in the stair is closed only for the head changes, inside an agreed impairment window. While the valve is closed, no guest room on that floor is occupied; guests are moved and the rooms blocked in the PMS before the valve is shut. The floor is drained, a fire watch patrols the whole floor while it is impaired, and the valve is reopened and the flow switch tested the same shift. Every planned impairment is notified in advance to the hotel's impairment coordinator, the brand FLS contact, the alarm receiving centre and the property insurer as the policy requires; Civil Defense is notified as SBC 801 requires. Each isolation sits on a permit signed by the hotel's engineering team.

Example layout. Real zones, routes and periods are agreed with your engineering, housekeeping and front office teams.

Quality, health, safety and environment

Site controls on an occupied floor

A hotel's engineering team is responsible for the building every hour of the day. Our controls are built to keep them in charge of it while we work.

Permits to work
Hot work, work at height, electrical work and tank entry each need a permit issued by the hotel's engineering team and held by our site supervisor. No permit, no work. Night-shift permits are issued before 18:00 by the hotel's authorised engineer and are valid only for the named zone, crew and night. The hotel's duty engineer stays on site through the night and is not sent to guest calls, because nothing is re-energised without the hotel's lock and signature.
Hot work
We design the flame out first: press-fit and grooved joints instead of brazing and welding wherever the specification allows. Where hot work is unavoidable, combustibles are cleared or covered, an extinguisher and fire blanket are at the point of work, the area's detection is handled as a logged impairment, and a fire watch stays for at least 60 minutes after the last spark, with a final check before the permit closes.
Confined spaces
Tank and pit entry is a confined-space permit: the air is gas-tested before and during entry, forced ventilation runs, a trained attendant stays at the hatch and a written rescue plan is in place before anyone goes in.
Isolations
Water and power are isolated as close to the work as the building allows: room circuits, branch valves, or each fan coil's own valves where coils are fed from vertical risers, leaving the risers and boards that other floors depend on in service. Where that can't be done, such as a sprinkler floor valve, a riser or main switchboard work, the isolation is a planned shutdown agreed in writing with the hotel. Every electrical isolation is locked with a multi-lock hasp: our authorised person fits the isolation lock, every worker in the zone adds a personal lock, and the hotel's duty engineer adds the hotel's lock. Circuits are proved dead at the point of work (live-dead-live). Locks come off in reverse order, and the system goes live only after the hotel's duty engineer has signed the permit back. In older buildings, the valves we plan to rely on are test-closed during the survey; where one won't hold, the method uses a pipe freeze or line-stop.
Hazardous materials and refrigerant
In buildings from before 2000 we sample for asbestos-containing materials before any ceiling, riser or plant room is opened; anything found is removed by a licensed specialist before our works start in that zone. Refrigerant from replaced chillers and split units is recovered by certified technicians, logged and sent for reclaim. It is never vented.
Crane lifts
A single planned lift, booked as an exception to the quiet hours and agreed with the general manager two weeks ahead. The crane comes with its third-party inspection certificate and a certified operator and rigger, the lift plan is signed by our appointed person, the exclusion zone is barriered at street and roof level, the traffic and municipality permits are in hand, and the lift is called off if wind exceeds the crane's limit.
Stop on request
The hotel's duty manager can stop noisy work on any floor by calling our site supervisor. Work stops while the call is still open. The stop is recorded the same day, with the complaint, room number and stop time, and countersigned by your duty manager; any change to a floor's return-to-sale date is put to you in writing, with its cost effect, before work resumes. It also goes into that week's report to the general manager.
Daily coordination
A short meeting each morning with engineering, housekeeping and front office: arrivals, events, rooms off sale, deliveries and anything noisy planned for the day.
Guest communication
Front office gets a one-page note each week saying which rooms are off sale, what guests may hear and when, and what to say. Bookings that would land next to the works are moved before the guest arrives.
Ballroom, F&B and kitchens
Works on the ballroom and kitchen levels are blocked out against the banqueting calendar eight weeks ahead. No shutdown of kitchen extract or a ballroom air handler within 48 hours of a confirmed event, no shutdown night booked on a night with a wedding or late ballroom event, and catering and sales get the same weekly note as front office.
Delegation and VIP stays
When the hotel hosts a delegation or a security-led event, we freeze work on the affected floors, or the whole building if your security team asks, from the time they set. Crews, materials and hoarding doors stay locked off. A freeze can start on 24 hours' notice. It is recorded the same day and countersigned by your duty manager, and any change to the floor return dates is put to you in writing, with its cost effect, before work resumes; the freeze and its days also appear in the weekly report.
Our people in your hotel
Every worker is registered with hotel security before day one, wears photo ID and a clean uniform, and enters through the staff entrance. No use of guest lifts, toilets or outlets, no contact with guests and no photography in guest areas. Keys are signed out daily. Breaks, prayer and meals happen in a back-of-house area agreed with the hotel. Any breach removes the person from site the same day.
Inspections
An inspection and test plan agreed before work starts, with hold points before anything is closed up. Your engineer can stop us at any hold point.
Witnessed testing
Pressure tests, fire alarm cause-and-effect and HVAC balancing are done with the hotel watching, and Civil Defense where their witness is required. Results are recorded on signed test sheets.

An example day on an occupied floor

  1. Deliveries and waste down the service lift, before housekeeping needs it.
  2. Permits issued. Isolations checked with the hotel's duty engineer.
  3. Coordination meeting with engineering, housekeeping and front office.
  4. After the floor's last check-out: the agreed period for noisy works opens, as set with the executive housekeeper.
  5. Second delivery slot: at a time set with housekeeping, so it never meets their heaviest use of the service lift.
  6. HSE and quality walk. Hold points inspected before anything is closed up.
  7. Before the first arrivals: the period closes. Quiet works only.
  8. Zone cleaned, detectors reinstated, permits closed, note left for the night engineer.

Example timings for Sunday to Thursday. Each hotel sets its own; the weekend and Ramadan follow their own times.

If something goes wrong

Before any drain-down or refill, the floor below is checked, ceilings near the works are protected, and wet vacs and spill kits are on the floor. Refills are done slowly, at a manned valve, with someone watching the floor below. If water escapes, the branch is shut at once, the duty manager is called, and affected rooms are logged and dried before they go back on sale.

If a fire alarm is triggered by our works, our supervisor goes straight to the fire command centre to confirm the cause with the duty manager.

Who is told, and when. The general manager is told at once, and the owner within 2 hours, of any injury, an evacuation, a loss of cooling, power or water lasting over 30 minutes, an impairment past its permitted window, or a positive water test. A written incident note follows within 24 hours, with the time, cause, photos, affected rooms and room-nights lost. Every incident and near miss is also in that week's report (CT-09) with the corrective action.

Planned shutdowns

A shutdown night, from 23:00 to 06:30

Some work can't be isolated at a branch: a main switchboard, a sprinkler floor valve, a chilled-water header. That work is a planned shutdown, agreed with you in writing first and run overnight, with a go/no-go call, a point of no return and a deadline to back out. No shutdown is booked on a night with a wedding or late ballroom event, and during Ramadan there are no shutdowns unless the general manager agrees one in the quiet hours after suhoor. A named CORETECH night supervisor is on site from the first isolation to the last permit closed.

Example: main LV board, section B, on a board whose form of separation lets one section be worked dead while the other stays live; otherwise the whole board is shut down. No work is done on live busbars.

  1. Letters delivered to affected guests; night permits issued; pre-shutdown checks signed against the dependency checklist.
  2. Window opens. Temporary generator on load and proved; one guest lift and the firefighting lift transferred to the generator and kept in service; other lifts on affected circuits brought to ground and locked off.
  3. Go / no-go Call with the duty manager and duty engineer: late arrivals, events, weather and spares on site. If any item is red, we stand down and rebook.
  4. Point of no return Section isolated to the written switching programme, read back by two people, locked, tagged and proved dead.
  5. Works.
  6. Back-out deadline If the work isn't ready to re-energise, the section goes back on its original supply.
  7. Re-energised in reverse order, each outgoing way checked.
  8. Lifts, fire panel, BMS and kitchen cold rooms confirmed healthy by the hotel's duty engineer.
  9. Permits closed and the night report left for the morning meeting, before breakfast service is busy.

Example timings. Night crews are inducted, badged and listed with hotel security before they arrive, use only the service lift and back-of-house routes, and shifts are capped so no one isolating or re-energising plant is past 12 hours on duty.

Before anything is switched off: what depends on it

  • Lifts: one guest lift and the firefighting lift stay in service on the generator; the other cars are recalled and the rescue procedure briefed.
  • Fire alarm panel and voice evacuation: battery autonomy tested that week; emergency lighting duration checked.
  • PMS, key-card encoders, telephones and the Wi-Fi core: on UPS or the generator.
  • Kitchen cold rooms and freezers: temperatures logged, doors kept shut.
  • Access control and CCTV: fail-safe status of each door confirmed with security; recording kept running.
  • Guests on powered medical equipment: anyone who has told the hotel is moved or informed in advance by front office.

Each item is ticked on the isolation certificate by the hotel's duty engineer. The certificate and switching programme form part of the method statement (CT-07).

Reporting

The weekly report your general manager receives

One page every week of the works. It goes to the general manager and, at the same time, to the owner or asset manager, so nobody hears a different story; the general manager can forward it to the brand's area office as it stands. The rows are fixed; the figures come from your project.

Weekly report to the general manager and ownerCT-09 · example format
Rooms returned to sale
This week, against the phasing plan
Rooms out next week
By room number, with room-nights out of inventory
Noisy-works days next week
Floors, days and hours, for front office and sales
Guest complaints linked to the works
Count, rooms, any stop on request and the action taken
Noise and vibration
Readings taken, and any rooms added to the sold-last zone
Safety, permits and impairments
Incidents and near misses, fire-system impairments and when they were cleared
Variations awaiting approval
Each one with its value in SAR and the decision needed; the forecast final cost is in the monthly cost report (CT-25)
Programme status
On time or days behind, late room releases recorded, and the updated programme
Example format. Your report carries your hotel's figures and is issued every week of the works.

Standards

The documents we work to

We work to these, with design by licensed engineering offices where a stamped design is needed. On most jobs we build to your consultant's design and produce the shop drawings; where design is in our scope, the contract says so and the design is stamped by a licensed engineering office. We do not issue approvals: Civil Defense approvals come from Civil Defense, and brand approvals come from the brand.

ReferenceWhat it covers on a hotel jobHow we handle it
SBC 401 · 501 · 701Saudi Building Code: electrical, mechanical, plumbing Requirements for everything we install or replace: cabling and boards, chilled water and air systems, water supply and drainage. Shop drawings and submittals checked against the relevant parts before procurement, such as fresh air rates against the SBC 501 ventilation tables, and the same parts used as the test criteria at commissioning.
SBC 801 and Civil DefenseThe Saudi Fire Protection Code, including Salamah safety licence renewals Fire detection and alarm, sprinklers, fire pumps, escape routes, emergency lighting and smoke control. FLS drawings stamped by a licensed engineering office and approved by Civil Defense before work starts. Fire systems installed only by Civil Defense-licensed contractors under our supervision. Escape routes kept open through every phase. Inspections prepared and attended.
SBC 601Energy conservation Equipment efficiency, insulation and controls for cooling, ventilation, hot water and lighting. Replacement plant is selected and checked against it before it is ordered.
Brand PIPBrand standards and property improvement plans Room comfort, power and data points, lighting levels, life safety and back-of-house standards set by the operator. A gap survey of the building against the brand's technical standard, then a priced technical scope for each PIP line. Drawings and key equipment submitted to the brand's technical services before ordering; the brand's opening inspection prepared and attended.
Operator, brand and insurer site rulesConstruction in an operating hotel, and FLS The rules for contractors on site set by the operator, the brand and the property insurer: hot work, fire watch, impairment notification and guest-area protection. Applied together with SBC 801 and Civil Defense requirements; where they differ, the more stringent governs. Every planned impairment is notified in advance to the hotel's impairment coordinator, the brand FLS contact, the alarm receiving centre and the property insurer as the policy requires; Civil Defense is notified as SBC 801 requires.
Ministry of TourismLicensing and classification requirements The technical items a licence or classification visit looks at, such as cooling, hot water, emergency power and fire safety in guest areas. Those items checked and closed out before the visit, using the technical gap report (CT-03). The licence and classification are the ministry's decision.

What you receive

The document register

One register and one set of codes for every service; each service page lists the documents that apply to it. Everything is issued as PDF, and drawings also in their native CAD format, so your next contractor isn't starting from scratch. Specimen pages, built on the same 176-room reference hotel, are linked from five of the documents below.

DocumentWhat it containsWhen you receive itWho signs
CT-01
Condition report
Specimen page (PDF)
Each system rated on site, with its remaining life, photos and the risks found; immediate items and red flags listed separately; energy and utility use After the survey Our MEP engineer, reviewed with your chief engineer
CT-02
CapEx plan
Replacements and upgrades by year, each line with a budget estimate, its basis (quote, unit rate or allowance) and a contingency, and what happens if it waits With the condition report Our project manager and QS; approved by the owner or asset manager
CT-03
Technical gap report (PIP, classification, code)
Specimen page (PDF)
The building checked against a standard: each line of a brand's property improvement plan (PIP), each Ministry of Tourism classification item, or each code item, with the current condition, the work needed and a price. Plus a risk register: provisional quantities at tendered rates, remeasured, for work that can be measured only once opened up (such as PQ-01 branch valves, PQ-02 fire-stopping), and named provisional sums for what can't yet be defined (such as PS-01 sprinkler alterations) Before you commit Our project manager; reviewed with your director of engineering
CT-04
Design approvals and brand submittals
Stamped FLS drawings with the Civil Defense approval, and on brand jobs the MEP and FLS submittal package with the brand's comment log Before anything is ordered Licensed engineering office; approved by Civil Defense and the brand's technical services
CT-05
Shop drawings and material submittals
Every item approved before it's ordered: switchboards with design verification from the original manufacturer and routine verification of each board, witnessed at the factory (IEC 61439); materials with SASO conformity Before ordering Our MEP engineer; approved by your engineer or consultant
CT-06
Phasing plan and room release schedule
Specimen page (PDF)
Which rooms come off sale and when, room-nights out of inventory by week, and the dates each floor is handed to us and returned; a late release or a moved quiet period is recorded the same day Before work starts, updated weekly Our project manager; signed by the general manager and revenue manager
CT-07
Method statements and isolation plans
The works plan for each floor, isolations with multi-lock hasp lock-out/tag-out, isolation certificates with the dependency checklist, switching programmes for shutdown nights, the fire-system impairment procedure, permits and risk assessments Before work starts Our project manager; agreed with the director of engineering
CT-08
Inspection and test plan
Hold points, checks and sign-offs for each system Before work starts Our HSE/QA lead; agreed with your engineer
CT-09
Weekly report to the general manager and owner
Specimen page (PDF)
Rooms returned against plan, rooms out next week, noisy-works days, guest complaints and stops on request, safety and impairments, variations awaiting approval, programme status Every week of the works Our project manager; to the general manager, the owner or asset manager, and the director of engineering
CT-10
Mock-up room sign-off
Agreed details, photos and the signed checklist every floor is built to Before rollout Owner's representative, director of engineering and, on brand jobs, the brand
CT-11
Test and commissioning records
Checklists, functional and integrated test sheets: pressure and flood tests, insulation resistance, fire alarm cause-and-effect; the testing, adjusting and balancing (TAB) report with airflow and fresh air per room and supply and return water temperatures on every floor handed back; trend extracts; and the water flushing log and disinfection certificate for each floor returned to sale At commissioning, zone by zone Our engineer and yours, plus Civil Defense where they witness
CT-12
FLS inspection pack
Test records and approved drawings set out for Civil Defense, then copies of the Civil Defense certificates and the Salamah safety licence Before the inspection; certificates after it Our MEP engineer; inspected by Civil Defense
CT-13
Brand compliance checklist
The brand's technical checklist completed, snags closed, ready for the brand's opening inspection Before opening Our project manager; approved by the brand's technical services
CT-14
Taking-over certificate and snag close-out
Each zone accepted with its snags closed. Return to sale is a separate sign-off by your chief engineer and executive housekeeper At handover of each zone Your owner's representative, on our application
CT-15
As-built drawings
Drawings updated to what was actually installed and how it is isolated, in PDF and native CAD At handover of each zone Our MEP engineer
CT-16
O&M manuals and training record
Equipment data, maintenance schedules, the spares list and the training record for your team Draft two weeks before testing; final at handover Our project manager; received by your director of engineering
CT-17
Spares, attic stock and tools
Handed over against a list, with special tools and keys At handover Signed receipt by your engineering team
CT-18
Warranty register and defects close-out
Each manufacturer warranty with its own start date, shown beside the zone's taking-over date and defects period so any gap is visible; the defects close-out certificate at the end of the defects period At handover; close-out at the end of the defects period Our project manager; accepted by your owner's representative
CT-19
Asset register
Every asset with its tag, location, make, age and condition, in a format your maintenance system can import At handover, or in month one of a maintenance agreement Our maintenance engineer; agreed with your chief engineer
CT-20
PPM year plan
Planned preventive maintenance (PPM) for every asset in the agreement, by month, with statutory inspections listed separately In month one of a maintenance agreement, then yearly Our maintenance engineer; agreed with your director of engineering
CT-21
Signed job sheets
Each planned and reactive job: what was found, what was done, parts used and the time taken With each job Our technician; countersigned by the hotel's duty engineer
CT-22
Monthly maintenance report
Specimen page (PDF)
PPM completed against plan, statutory inspections, reactive calls and response, repeat faults and recommendations Every month of a maintenance agreement Our maintenance engineer; received by your director of engineering
CT-23
FLS maintenance records
Inspection, testing and maintenance records for fire and life safety systems, kept ready for Civil Defense and the Salamah safety licence renewal As each inspection or test is done The Civil Defense-licensed contractor that does the work; held by your director of engineering
CT-24
Annual condition review and lifecycle plan
Each system re-rated once a year, with the maintenance lifecycle plan looking five years ahead Once a year of a maintenance agreement Our maintenance engineer; reviewed with your director of engineering
CT-25
Monthly cost report
Contract sum, approved and pending variations with their SAR value, provisional sums against allowance, contingency drawn and remaining, forecast final cost and a three-month cash-flow forecast, in PDF and Excel Every month of the works, with each payment application Our project manager and QS; to the owner or asset manager