Worked example — illustrative, not a completed project

How we would renew eleven guest floors and three chillers while a 176-room hotel keeps trading

A case-study dossier filled with the reference hotel used across this site: the building model, the phasing chart and the specimen documents. It is not a client, a site or a result. Every figure below is either a stated assumption or an output of our phasing model.

Dossier
EX-01
Status
Illustrative
Building
Reference hotel · G+12, Riyadh · 176 keys
Scope
Guest-floor MEP, L2–L12, and replacement of three roof chillers, while trading
Basis
The site's method, specimen documents CT-01, CT-03, CT-06, CT-09 and the phasing model
Revision
A
Client data
None

NOTE · ILLUSTRATIVE

Read this first

We have not yet completed a project we can publish, so we will not show one. This page uses the same 176-room reference hotel as our 3D model, the phasing chart on the home page and the specimen pages, and walks it through our method in the format we will use for completed projects. What is real here is the method, the document formats and the arithmetic of the model. What is not: a client, a site, dates, prices, or anything measured.

01

Brief: two jobs, one building that never closes

The survey rates every system on site. In this example the condition report (CT-01) finds that the fire alarm and detection need replacing now, the guest-room fan coils and the generator's transfer switch follow in year 1, and the chillers have two to three years left, to be replaced one at a time in the winter of year 2.

The brief that follows has two parts. First, renew the guest-floor services on all eleven guest floors, L2 to L12: fan coils, detection and the brand's technical PIP lines for each room, reaching the branch valves and the ceilings. Second, replace the three air-cooled chillers on the roof. The hotel keeps selling rooms throughout, and the building keeps its cooling in a city designed for 48 °C.

The problem to solveHow many rooms can come off sale, when, and for how long, and how each chiller can come out without the hotel losing its cooling.

02

Constraints, as the rest of this site states them

Nothing here is new. Each constraint is one our method already commits to, and links to where it is set out.

  • PARAM · 176 KEYS TRADING

    The hotel stays open

    Rooms come off sale only as the signed phasing plan says, floor by floor, and each floor carries its own return-to-sale date.

    Step 3, phasing plan
  • PARAM · 48 °C DESIGN AMBIENT

    Cooling sized for a Riyadh roof

    New chillers are selected at the 48 °C design ambient and specified to keep running, unloaded, up to 52 °C on a hot roof, with coated condenser coils and spacing checked for hot-air recirculation.

    MEP contracting
  • PARAM · RISERS LIVE

    Isolate at the branch, never the riser

    Each floor is isolated at its own board and at the valves serving its rooms, so the risers stay live for the floors above and below. A riser is drained only in a planned shutdown.

    Working in a live hotel
  • PARAM · QUIET HOURS

    Noise only in the agreed period

    Noisy work runs after the floor's last check-out and stops before the first arrivals, as set with housekeeping. The duty manager can stop it on any floor with one call.

    Site controls
  • PARAM · CRANE-LIFT WINDOW

    One planned lift per chiller

    Each swap is a single crane lift, booked as an exception to the quiet hours and agreed with the general manager two weeks ahead, in the lower-load months of November to March, away from Riyadh Season peaks. It is called off if wind exceeds the crane's limit.

    Chillers, on the home page
  • PARAM · CIVIL DEFENSE

    Approved before, witnessed after

    The FLS drawings for the new detection are stamped by a licensed engineering office and approved by Civil Defense before installation; fire systems are installed only by Civil Defense-licensed contractors; a sprinkler floor valve is closed only when no guest room on that floor is occupied.

    Regulations and standards
  • PARAM · EVENTS AND RAMADAN

    The calendar comes first

    No shutdown night on a night with a wedding or late ballroom event, and no shutdowns in Ramadan unless the general manager agrees one in the quiet hours after suhoor.

    A shutdown night
  • PARAM · 70% OCCUPANCY (EXAMPLE)

    Example inputs, labelled as such

    The revenue figures use the phasing chart's example values: an average room rate of 450 SAR, 70% occupancy and 4 high-demand nights a month. They are not a hotel's figures.

    The phasing chart

03

Options considered, and how the choice is made

In a real job each choice is signed by the person who owns it. Here we show the options, the test that decides between them, and what the example assumes.

DecisionOptionsHow the choice is madeIn this example
Floors out at a time Two floors at a time: 24 weeks, 144 rooms selling at peak. One floor at a time: 44 weeks, 160 rooms selling. Your revenue manager picks the mix in the phasing plan (CT-06), against the occupancy forecast. Two floors at a time, two crews, from L12 down.
How a floor comes out Full-floor release, or part-floor zones behind a sealed hoarding. Full-floor when the work reaches the riser branches, ceilings or bathrooms below; part-floor when it stays inside the rooms. Full-floor release: the scope reaches the branch valves and ceilings.
Cooling during each chiller swap The two remaining chillers carry the load, or temporary cooling is brought in for each swap. The survey checks the remaining chillers against the load in the swap months, before you approve the budget. Assumed: the two remaining units carry the winter load. A real survey would have to show it; if it doesn't, temporary cooling is priced in.
Replacement chillers Equipment options compared at the 48 °C design ambient, against the SBC 601 minimum efficiency and on refrigerant. Checked at submittal (CT-05) and approved by your engineer before anything is ordered. No make or model is named in an illustrative example. How equipment options are compared
Pipe joints on guest floors Brazed or welded joints, or press-fit and grooved joints. We design the flame out first, wherever the specification allows. Press-fit and grooved; any unavoidable hot work runs under permit with a fire watch.

04

Phasing: guest floors in year 1, chillers in the winter of year 2

Each floor gets three weeks of works and one week of testing, starting from level 12, with two floors out at once and two crews starting two weeks apart. This is the same programme as the specimen phasing plan.

Week Back on sale 123456789101112131415161718192021222324L12wk 5L11wk 7L10wk 9L9wk 11L8wk 13L7wk 15L6wk 17L5wk 19L4wk 21L3wk 23L2after 24 SellingOff sale160161601614432144321443214432144321443214432144321443214432144321443214432144321443214432144321443214432144321601616016SellingWorksTestingHanded back
CT-06Phasing strip, guest floors L2–L12Two floors at a time · 24 weeksIllustrative

Chillers: one at a time, November to March of year 2

  1. CH-1Lift date chosen from the occupancy forecast. Old unit out and new unit in on one planned crane lift; connected, commissioned and run with the other two.
  2. CH-2Starts only once CH-1 is running with the others. Same lift, connection and commissioning sequence.
  3. CH-3Starts only once CH-2 is running. Witnessed tests and the TAB report close out the chilled-water plant (CT-11).

No dates are given: in a real plan they come from your forecast and events calendar.

06

“Results”: what the phasing model computes, not what happened

These are outputs of the same model as the phasing chart on our home page, run on the programme above. Nothing here was measured on a building.

Programme, guest floors
24 weeks
MODELLED
Fewest rooms selling, weeks 3–22
144 of 176
MODELLED
Room-nights off sale, whole programme
4,928
MODELLED
Absorbed by rooms still selling *
4,280 room-nights
MODELLED
Displaced on high-demand nights *
≈ 648 room-nights
MODELLED
Rooms revenue displaced *
SAR ≈ 291,630
MODELLED

* At the example inputs: 450 SAR average room rate, 70% occupancy, 4 high-demand nights a month spread evenly through the year. The worst case, with every night full, is 2,217,600 SAR. The model leaves out the higher rate after refurbishment and any food and beverage spend.

Rooms selling and rooms off sale, week by week (modelled)
  • Rooms selling
  • Off sale (works and testing)
050100150176Week 1: 160 selling, 16 off sale1Week 2: 160 selling, 16 off sale2Week 3: 144 selling, 32 off sale3Week 4: 144 selling, 32 off sale4Week 5: 144 selling, 32 off sale5Week 6: 144 selling, 32 off sale6Week 7: 144 selling, 32 off sale7Week 8: 144 selling, 32 off sale8Week 9: 144 selling, 32 off sale9Week 10: 144 selling, 32 off sale10Week 11: 144 selling, 32 off sale11Week 12: 144 selling, 32 off sale12Week 13: 144 selling, 32 off sale13Week 14: 144 selling, 32 off sale14Week 15: 144 selling, 32 off sale15Week 16: 144 selling, 32 off sale16Week 17: 144 selling, 32 off sale17Week 18: 144 selling, 32 off sale18Week 19: 144 selling, 32 off sale19Week 20: 144 selling, 32 off sale20Week 21: 144 selling, 32 off sale21Week 22: 144 selling, 32 off sale22Week 23: 160 selling, 16 off sale23Week 24: 160 selling, 16 off sale2432 off sale144 sellingProgramme week
Week-by-week table
Modelled rooms selling and off sale for each week of the example programme
WeekWorksTestingRooms sellingof which sold lastRooms off saleRoom-nights off sale
1L12–1601616112
2L12–1601616112
3L12, L11–1441632224
4L11L121441632224
5L11, L10–1443232224
6L10L111441632224
7L10, L9–1443232224
8L9L101441632224
9L9, L8–1443232224
10L8L91441632224
11L8, L7–1443232224
12L7L81441632224
13L7, L6–1443232224
14L6L71441632224
15L6, L5–1443232224
16L5L61441632224
17L5, L4–1443232224
18L4L51441632224
19L4, L3–1443232224
20L3L41441632224
21L3, L2–1441632224
22L2L3144032224
23L2–1601616112
24–L2160016112
Total room-nights off sale4,928

Two modelled alternatives

One floor at a time
44 weeks instead of 24; 160 rooms selling instead of 144; the same 4,928 room-nights off sale in total.
Level 9 runs two weeks late
26 weeks; 224 more room-nights off sale, of which about 29 are displaced, about 13,255 SAR at the example inputs. That is why every floor carries a return-to-sale date and any slip is in the weekly report.

NOTE · PUBLISHING

When we complete real projects, they will be published in this format.

With the client's permission, and with measured figures in place of modelled ones: rooms actually off sale, the weekly reports as issued, and the test records as signed. Until then, we can build this dossier for your own building, starting with a survey.

EX-01 Rev A · first issue. Built from the reference hotel used across this site. Not a CORETECH project; no client data; figures are assumptions or model outputs. Illustrative