Brand conversions and refurbishment for open hotels

When a hotel changes flag or gets a refurbishment, the expensive surprises sit above the ceiling and inside the risers. We survey what is there, price the gap to the brand standard line by line, and build it floor by floor while the rest of the hotel keeps selling rooms.

  • Re-flagging and brand property improvement plans (PIPs)
  • Partial or full room renovation
  • Buildings converted into hotels
PIP gap, typical king roomRoom 907, floor 9 · works zone 907-912 of 901-916
A B C 1 2 CORRIDOR 907 PD BATH ENTRY BEDROOM 1 800 8 400 4 200 1 2 3 4 5 6 1 2 3 4 5 6 Existing Brand standard
03

Existing

Weak flow on upper floors, hot water slow to arrive, worn mixer.

Brand standard

Thermostatic mixer; flow and hot-water time tested at the top-floor room against the brand minimum; fittings meet SBC water efficiency without dropping below it.

CT-03King room 907 · PIP gapSCALE 1:50 (A3)Example

Drag the line across the room, or pick an item. Brand standards differ by brand and tier; this is an example only.

What's included

The technical side of a PIP, start to finish

Your interior designer designs the room and your FF&E supplier supplies the loose furniture. We build and connect the MEP and every interface their work plugs into, hangs from or hides behind, coordinated on one set of drawings so the ceilings only open once.

AreaWhat we doTypical items
Technical survey and gap pricingWalk every system against the brand's technical standards and the PIP, then price each gap item so the owner can see where the money goes.Sample rooms per floor, plant rooms, risers, roof, back of house, life-safety walk-through
HVAC replacementReplace or refurbish plant and room units, re-balance the air and water side, and tie controls back to the BMS.Chillers, AHUs, fan coils, thermostats, ductwork and grilles, testing and balancing
Electrical upgradesCheck the incoming supply and main switchboard can carry the new loads, then rewire rooms to the brand's power and lighting layout.Room distribution boards, bedside and desk power, USB, key-card switches, LED lighting and controls
Fire and life safety upgradesBring detection, alarm and suppression in line with Civil Defense requirements and the brand's FLS standard. FLS drawings are prepared and stamped by a licensed engineering office and approved by Civil Defense before work starts; fire systems are installed only by Civil Defense-licensed contractors, under our site management, then tested and presented for inspection.Sprinkler coverage throughout, including guest rooms and corridors; in-room alarm audible at the pillow (sounder bases or voice evacuation); visual alarms in accessible rooms; self-closing fire-rated guest-room and corridor doors; stair pressurisation and corridor smoke control; emergency lighting duration; fire-stopping of every new penetration
Plumbing and hot waterFix pressure and temperature at the top floor before the new fixtures go in, so the new showers actually perform.Booster sets and pressure-reducing valves, hot water plant and return loop, fixtures that meet water-efficiency rules at the brand's shower flow, drainage
Guest technology and extra-low-voltage (ELV) systemsCoordinate the brand's approved lock, Wi-Fi, IPTV, room-management and CCTV vendors: we provide the cabling containment, power and connections, run their work under our programme and the permits, agree who pulls each cable before the floor is opened, and test the interfaces to the PMS, POS and lock server before a floor returns to sale. The systems themselves are installed by the brand's or your nominated specialists.ELV containment and IDF rooms, Wi-Fi backbone and access-point power, key-card holders, door-lock power and encoders, IPTV head-end interface, CCTV interface, GRMS thermostats, PMS interface tests
Lifts, LPG and pool plantInterface and coordination only. The lift maker or a licensed lift contractor, the licensed gas contractor and the pool specialist keep their scope; we put their shutdowns in the same phasing plan and connect and test the points where they meet our work.Lift-out-of-service days, fire recall and firefighting lift tested with the alarm, gas shut-off interlocks, pool plant power and controls
Testing, commissioning and re-flaggingWitnessed tests on every floor before it goes back on sale; for the brand's opening inspection we prepare the compliance checklist and attend.Test records per floor, brand inspection snag list, as-built drawings, O&M manuals

Design interface matrix

Designer designs, supplier supplies the loose furniture, CORETECH builds and connects the MEP and the interfaces. Joinery and FF&E supply stay with the owner's appointed designer and suppliers; who supplies each item is confirmed per project.

ItemDesigner specifiesFF&E supplier providesCORETECH provides and connects
Headboard with reading lights and USBDesign, fitting positions, finishThe headboard with its fittingsPower and switching at the agreed positions, connection and test
Bedside control panelPosition and faceplateNightstand cut-out, where built inBack box, wiring to lighting, curtains and the room controller
TV and wall bracketHeight and positionBracket or TV unit, as the owner ordersWall backing, power and data, IPTV interface test
Minibar in the millworkMillwork design and ventilation slotsMillwork, by the owner's joinery supplierSocket inside the unit, kept live on the key-card circuit
Motorised curtain trackTrack, pelmet and fabricTrack, motor and curtainsCeiling fixing support, power and control wiring
Vanity mirror with demister and backlightMirror design and sizeThe mirror unitSupply on the bathroom lighting circuit, protected and tested
Decorative lamps and ceiling fittingsFittings and positionsLamps and decorative fittingsSwitched sockets, ceiling supports and connections

Positions are fixed against the approved headboard and millwork shop drawings before first fix, not after. The interior designer and the FF&E supplier join the mock-up room sign-off.

Typical triggers

Usually there is a date on the calendar

A franchise signing, a handover between operators, a reopening. The technical scope is the part that moves that date, so it needs pricing early.

  • An independent hotel has signed with an international brand, and the PIP arrives with a technical section nobody on site can price.

  • The management company is changing, and the incoming operator's audit lists items the outgoing one never raised.

  • Guest reviews keep mentioning a noisy air conditioner, a weak shower and nowhere to charge a phone.

  • An office or residential building is being converted into a hotel, and the services were never designed for guest rooms.

  • The owner wants to renovate a few floors at a time, without closing, and needs to know how many rooms come out of inventory each month.

  • A reopening date is set, and the fire and life safety systems have to pass Civil Defense inspection before it.

How the engagement works

One mock-up room before a single floor is opened

The mock-up room is where the brand, the operator and the owner agree what finished looks like. After that, every floor is built to the same sheet.

  1. Survey and gap report

    Sample rooms on every floor, all plant rooms, and the PIP read line by line.

  2. Scope, phasing, price

    A priced scope and a phasing plan built from your occupancy forecast, with room-nights out of inventory by week.

  3. Design approvals and brand submittal

    MEP and FLS drawings and key equipment submittals sent to the brand's technical services for review, and stamped FLS drawings approved by Civil Defense. Comments are closed before anything is ordered.

  4. Mock-up room

    One room finished and tested first, then signed off before rollout.

  5. Floor-by-floor works

    Each floor isolated at its own branch valves and board where the risers allow it (where fan coils are fed from vertical risers, isolations are planned by riser stack), guest routes kept separate, noisy work in agreed hours.

  6. Test and hand back

    Witnessed tests per floor, a taking-over certificate from your owner's representative, then the rooms go back to housekeeping.

Who signs off
Gap report and priced scopeOwner, with the operator's review
Design submittalBrand technical services; FLS drawings by Civil Defense
Mock-up roomBrand technical services and the operator, with your interior designer and FF&E supplier
Taking-over certificate per floorOwner's representative, on our application
Return to saleHotel chief engineer and executive housekeeper, after the joint inspection
Fire and life safety systemsCivil Defense inspection, which we prepare for and attend with you
Brand opening inspection and approval to openBrand technical services; we prepare the compliance checklist and attend
Tourism licence or classification visitMinistry of Tourism; technical items closed before the visit
Final handoverOwner's representative
ServiceProject contract

Brand conversion: technical scope

For hotels moving to a brand. Survey, PIP gap pricing, MEP and FLS works, and support through the brand's opening inspection.

ServiceProject contract

Hotel renovation

For existing hotels refreshing rooms or public areas. Technical scope, phasing around occupancy, works and handover per floor.

What you receive

A document trail the brand will ask for

Brand technical teams inspect against paper as much as against the building. These are the documents a conversion is contracted to produce, with the same codes as our full register.

RefDocumentWhat's in itWhen
CT-03PIP technical gap reportView a sampleEach PIP line with the current condition, the work needed and a price, grouped by system, plus a risk register that keeps provisional quantities (PQ: quantity × tendered rate, remeasured) apart from named provisional sums (PS: spent only on your instruction).Before you commit
CT-04Brand submittal and comment logMEP and FLS drawings and key equipment sent to the brand for review, with each comment and how it was closed; the Civil Defense FLS approval.Before procurement
CT-06Phasing plan and room release scheduleView a sampleFloor sequence, rooms and room-nights out of inventory per week, the dates each floor is released and returned, guest routes and work hours.With the price
CT-10Mock-up room sign-offAgreed details, photos and the signed checklist every floor is built to.Before rollout
CT-11Test and commissioning recordsHVAC testing and balancing, controls, power, FLS (fire and life safety) and water tests for each floor, witnessed and signed.Per floor
CT-13Brand compliance checklistThe brand's technical checklist completed, with snag items closed out.Before opening
CT-14Taking-over certificateEach floor accepted by your owner's representative with its snags closed, on our application.Per floor
CT-15 · CT-16As-builts and O&M manualsDrawings of what was installed, equipment data, spares lists, and the manufacturers' warranties, listed separately from our defects period.At handover

The full document register

Before you start a conversion

Can you price the PIP before we sign the franchise agreement?

Yes, and it is the best time to do it. The Hotel Technical Assessment (CT-01) gives you a priced gap report you can use in the negotiation with the brand, including items you may be able to phase or defer.

Do you handle interiors and furniture?

Your interior designer designs the room and your FF&E supplier supplies the furniture and joinery. We build and connect the MEP and every interface behind it, set out in the design interface matrix above, so ceilings, sockets and light positions match their drawings the first time.

How many rooms will be out of service at once?

That depends on the building, the riser layout and your occupancy forecast. We size each phase with your revenue and operations teams and write the rooms and room-nights out of inventory into the phasing plan, week by week. The home page has a worked example with one or two floors out at a time.

What if you find something above the ceiling we didn't price?

The mock-up room is opened up first, so concealed conditions are found before rollout pricing is fixed. What can be measured only once ceilings are open is a provisional quantity at a tendered rate and remeasured; what cannot yet be defined is a named provisional sum, spent only on your instruction.

Is our PIP kept confidential?

Yes. PIPs and brand standards are confidential, so we sign your NDA (or send ours) before reviewing them, and you can share them by email instead of uploading. Brand documents are used only for the gap report and returned or deleted afterwards.

Who installs the work?

Our engineers plan and manage the works and check them daily. Crews we prequalify install under the permits, and fire systems are installed only by Civil Defense-licensed contractors. You have one contract and one project manager, and CORETECH is liable to you for every subcontractor's work.

Codes we work to

The Saudi regulations and standards behind this service, with what each covers and how we apply it.

All regulations and standards

Start with the PIP

Send us the PIP and we will tell you what it means for the building

PIPs and brand standards are confidential. We sign your NDA before reviewing them, and you can send them by email instead of uploading.